ENERGIAKI PTOON SINGLE MEMBER S.A.

Energy production from renewable resources

 

 

 

Projects

Ptoon – Pyrgos – Anemomylos
“Ptoon – Pyrgos – Anemomylos” wind farm, with 40 MW capacity is located in the Municipalities of Orchomenos and Chalkida, Regional Entities of Viotia and Evia and consists of:
  • Eleven (11) Gamesa G97 – 2 MW wind turbines
  • Nine (9) Gamesa G87 – 2 MW wind turbines
  • Step-up Medium/High Voltage 20/150 kV substation
  • Control Building

Construction works were completed in February 2016 and the wind farm has been since operating, while the estimated yearly production amounts to 88 GWh.